Virtual IMS / 5GC

IP Multimedia Subsystem IMS Deplyment

  • Client US T1 Telco
  • Timeline 2017-2018
  • Scope End to End Program Delivery
  • Bueget $40M
Challenge

Inflight program with multiple issues resulting in client dissatisfaction, cost over-runs and demotivated project team

Strategy

Created a program strategy to change trajectory

  1. Program analysis
  2. Get well plan
  3. Stakeholder buy-in
Implementation

Worked with project managers and team to:

  1. Re-baseline & stakeholder handshake
  2. Change project culture & introduction of new tools (JIRA, Agile WOW)
  3. Program Governance structure implementation
  4. Stakeholder management
  5. Continuous tracking & monitoring

Program including Virtual vMTAS, vENM, vEDA, vGUI and VNF-LCM for Tier 1 Operator in US. Includes SW upgrades, expansions and new feature introductions including 5G